Everything appears to be in place for the start of the long-awaited project to tear down several abandoned IBM buildings at the company's former Endicott manufacturing hub.

Officials say the only thing delaying the multimillion-dollar demolition job now is a final review by the State Historic Preservation Office.

Ironically, New York state in December 2022 announced it would provide $6 million to the village of Endicott for the project.

At that time, Huron Campus site manager Chris Pelto hoped the demolition could get underway in a few months.

The east end of the planned demolition site on July 3, 2024. (Photo: Bob Joseph/WNBF News)
The east end of the planned demolition site on July 3, 2024. (Photo: Bob Joseph/WNBF News)
loading...

Logistical problems, including underground utility lines and equipment, delayed the start of the project. But those issues have been addressed.

Broome County Executive Jason Garnar said while the money has been secured to do the work, "we're waiting for SHPO (the state agency) to give us the green light."

Garnar told WNBF News that after the Huron Campus owners advised the agency that they planned to demolish five unused dilapidated buildings, the agency asked whether there were any ways the structures could be repurposed.

The county executive said the owners advised the state that "the buildings are too far gone, they've been condemned, they've been sitting there empty for 20 years." The agency was informed it would take "an infinite amount of money" to make the structures usable.

A building on North Street with the "International Business Machines" logo that was introduced in 1924. (Photo: Bob Joseph/WNBF News)
A building on North Street with the "International Business Machines" logo that was introduced in 1924. (Photo: Bob Joseph/WNBF News)
loading...

Garnar said he expects the historic preservation office to provide a response within "the next week or two." He anticipates the agency will allow the demolition to proceed.

The county executive said Governor Kathy Hochul is "incredibly supportive of this project." He said he's discussed the importance of the site with Hochul.

Garnar said "the quicker these buildings can come down, the quicker that the owners can work to develop the site."

The "Old Building Group" at the former IBM complex east of McKinley Avenue are to be demolished. Photo: Bob Joseph/WNBF News
The "Old Building Group" at the former IBM complex east of McKinley Avenue are to be demolished. (Photo: Bob Joseph/WNBF News)
loading...

Even as the officials go-ahead is awaited, workers from Gorick Construction are continuing to prepare the property for the planned demolition.

Knocking down the buildings with 550,000-square-feet of unused space will clear the way for creation of a 10-acre shovel-ready site for redevelopment.

WNBF NEWS VIDEO: A visit to North Street between McKinley and Hayes avenues in Endicott on July 3, 2024.

WNBF News Radio 1290 AM & 92.1 FM logo
Enter your number to get our free mobile app

Contact WNBF News reporter Bob Joseph: bob@wnbf.com. For breaking news and updates on developing stories, follow @BinghamtonNow on Twitter.

103 iconic photos that capture 103 years of world history

Stacker gathered some of the most iconic images from the past 103 years, beginning in 1918 and leading up to 2020 during the COVID-19 pandemic.

Gallery Credit: Rachel Cavanaugh & Elizabeth Ciano

LOOK: The oldest cities in America

Though the United States doesn’t have as long of a history as some Old World countries, it still has plenty of historical charm. Stacker brings you a list of the 50 oldest cities in America.

Gallery Credit: Annalise Mantz

LOOK: These Are the 50 biggest retailers in America

Stacker compiled a list of the 50 biggest retailers in the country, using retail sales data from Kantar, provided by the National Retail Federation.

Gallery Credit: Madison Troyer & Zack Abrams

More From WNBF News Radio 1290 AM & 92.1 FM