New Endicott Power Facility to Serve Data Center
Construction is continuing on an installation to provide more electricity to the Huron Campus in Endicott.
Site work for the modular natural gas fuel cell system between Clark Street and Watson Boulevard began last month. The facility is being built in a Huron parking lot west of Hayes Avenue.
California-based Bloom Energy is developing the system next to a NYSEG substation.
Chris Pelto, who oversees Huron Campus operations, said there's a need for more power at the site.
A Bloom Energy representative told WNBF News work on the 9.36 megawatt facility is expected to be completed by the end of this month.
He said the installation will provide power to a Global AI data center on the Huron Campus.
Dozens of power modules have been delivered to the construction site.
According to Bloom Energy, the fuel cells in its energy servers convert fuel into energy without combustion.
The fuel cells are combined to form stacks and the stacks are put together to form a module.
The system is designed to provide the type of reliable energy source data centers require.
WNBF NEWS VIDEO: The construction site near Clark Street in Endicott on March 13, 2026.

Contact WNBF News reporter Bob Joseph: bob@wnbf.com or call (607) 545-2250. For breaking news and updates on developing stories, follow @BinghamtonNow on Twitter.
See How School Cafeteria Meals Have Changed Over the Past 100 Years
Gallery Credit: Madison Troyer
YEAR IN REVIEW: 2025 in Powerful Photos
Gallery Credit: Stephen Lenz
CHECK THEM OUT: States With the Best and Worst Commutes
More From WNBF News Radio 1290 AM & 92.1 FM